Most Permit
Applications require at least the following items:
q Complete Application Form (signed by property
owner) and Fee
q Site Plan (include parking, trees &
landscaping, easements)
q Plot and Finish Grading Plan – 2 sets – Ref. City
Engineering Standards Vol. III, Part II, Section E and
Attachment D, D-1, D-2 and E)
q Foundation and Roof Plans
q Floor Plan (existing and proposed; label all
rooms)
q Elevation Plans (all sides, provide photos if
existing)
q Construction Section and Details (show framing and
footings)
q Electrical, Mechanical, and Plumbing Plans
q Structural Calculations – 2 sets
q Soils Report (new buildings, basements, hillsides,
other special
circumstances
as required by the Building Official) – 2 sets
q Job Specifications – 2 sets
q
Title 24 Energy Calculations, 2005 version (required
for all habitable or “conditioned” space) – 2 sets
q Fire Sprinkler Plan (sprinkled buildings only) – 2
sets
q Local Development Standards (curb, gutter,
sidewalk, driveway approach, street trees,
street
lights, etc.) – 4 sets
q School Impact Fees (residential > 500 sq. ft.)
q Traffic Impact Fees
q Local Development Costs
q Water and sewer fees (as applicable)
q Environmental Impact Assessment
q Description of Use
q NPDES Permit Compliance for construction and new
development and check lists
q Other
______________________________________________________